This schedule is subject to revision, particularly with regards to the entries listed beyond Finals week.
The items after August 1 are delayed while we work out a problem with printing on Solaris 2.5
Last updated on: Thu Jul 11 16:49:09 PDT 1996
| Dates | Event |
|---|---|
| May 2 - May 9 | Practice upgrading workstation to Solaris 2.5 |
| May 9 - May 16 | None; continue upgrade practice |
| May 16 - May 23 | Convert sycamore/poplar/deodar |
| May 23 - Jul 17 | Work out snags |
| Jul 17 | Convert 1/2 of ACL |
| Jul 17 - Jul 26 | Work out snags, convert rest of ACL |
| Jul 29 - Jul 31 | Prepare GCL for conversion |
| Aug 1 - Aug 9 | Upgrade GCL, work out snags |
| Aug 12 - Aug 16 | Convert Solaris 2.3 servers (bamboo and sycamore) |
| Aug 19 - Aug 23 | Convert faculty workstations |
| Aug 27 - Aug 28 | Upgrade sonia |
| Aug 29 - Aug 30 | Convert redwood, euphemia, oak |
| Sep 2 - Sep 6 | Convert julia |
| Sep 9 - Sep 13 | Convert PIC |
| Sep 16 - Sep 27 | Unresolved issues |
| --------------- | --------------------------------------------- |
| ??? | Upgrade joshua to UltraSparc 140 |
| ??? | Install new web server hardware |
Please send comments to jbence.